47 days, and where they go
Installers describe net metering as a utility bottleneck. The timestamps disagree. We tracked 210 rooftop applications across four discoms from customer signature to meter installation, and the utility held the file for a median of nine working days.
The resubmission loop
The dominant cost is not review time, it is the round trip. An application comes back for one missing annexure, sits in an installer's inbox for a week, goes back, and re-enters the queue at the bottom. Two and a half of those loops is most of a month.
We were not waiting on the discom. We were waiting on ourselves to notice they had written back.
Interconnection coordinator, 6 MW residential portfolio